Ministry boosts public investment disbursement to speed up projects
The Ministry of Transport is keeping a close watch on monthly public investment disbursement progress and transferring capital from projects with slow disbursement to more capable ones.
A stretch of the eastern wing of the North - South Expressway is covered with asphalt. (Photo: VietnamPlus)
Hanoi (VNA) 💮– To ensure 100% of public investment is disbursed as instructed by the Government, projects of the Ministry of Transport (MoT) are being accelerated by investors and management boards and even injected with more capital to speed up progress.
Accelerating disbursement for expressway projects
So far, the MoT has disbursed about 27.5 trillion VND (nearly 1.1 billion USD), or 44% of the 62.6 trillion VND from the central budget assigned to it, reported the MoT’s Department of Planning and Investment.
It said the National Assembly Standing Committee has approved an additional 8.68 trillion VND sourced from the increased sum of the central budget last year for MoT’s key projects. As much as 6.3 trillion VND of the funding is allocated for the North-South Expressway projects of the 2021 - 2025 period. Relevant ministries are finalising reports to be submitted to the Prime Minister so that the money could be provided this August.
Including the additional funding from the central budget, the capital assigned to the MoT this year totals 71.28 trillion VND.
Nguyen Vu Quy, Director of the Ho Chi Minh Road project management board – and investor of the Van Ninh - Cam Lo expressway project, said about 46% of this expressway project’s workload has been fulfilled. The average monthly disbursed value is 230 billion VND, 1.4 times higher than the planned pace.
He estimated that about 2.37 trillion VND will be disbursed for the project by the end of 2024, equivalent to more than 95% of the registered capital plan. By that time, the fulfilled workload will reach some 65 - 70% of the project’s contract value.
A bridge on the Can Tho - Hau Giang section of the North - South Expressway is under construction. (Photo: VietnamPlus)
Le Duc Tuan, Deputy Director of the My Thuan project management board – investor of the Can Tho - Hau Giang expressway project, noted a total of more than 6.43 trillion VND, equivalent to over 34% of the contract value, has been disbursed for expressway construction.
Under the 2024 plan, nearly 5 trillion VND will have to be disbursed for the project this year. More than 2.4 trillion VND, or about 48%, of the sum, has already been allocated. The management board is urging contractors to mobilise more manpower and equipment to speed up construction and ensure progress, he said.
Regarding two expressway projects traversing central Quang Binh province, the Vung Ang - Bung and Bung - Van Ninh sections have had over 58% and 51% of their workload completed, respectively, the Director of the Project 6 management board Tran Huu Hai said.
He added the management board has registered for another 1 trillion VND and 200 trillion VND to be respectively added to the Vung Ang - Bung and Bung - Van Ninh sections. The board and contractors are hastening construction so that the entire route from Bai Vot to Van Ninh could be open to traffic on April 30, 2025.
Injecting more capital to speed up projects
The disbursed sums for projects of the North - South Expressway are relatively high, but they mainly focus on facilities like bridges and tunnels on the route other than roads. As the rainy season is coming, investors need to accelerate road construction to ensure progress, said the Department of Planning and Investment.
Minister of Transport Nguyen Van Thang demands project management boards and investors work harder on investment disbursement. (Photo: VietnamPlus)
An official of the department pointed out the need to keep a close watch on monthly disbursement progress, transfer capital from projects with slow disbursement to more viable projects, and handle incapable investors, project management boards, and contracts that affect construction and disbursement progress.
The North - South Expressway is to have 100% of public investment disbursed by 2025. Minister of Transport Nguyen Van Thang said project management boards must maximise the disbursed funding and the completed workload. They also need to submit proposals regarding the projects needing more funds to MoT leaders so that capital is allocated on time./.
Prime Minister Pham Minh Chinh has asked for breakthrough solutions to fulfil the target of 95% in the disbursement rate of public investment capital in 2024.
Prime Minister Pham Minh Chinh on July 16 ordered ministries, central agencies, and localities to show higher determination in speeding up the disbursement of public investment capital, focusing on five aspects, including maintaining discipline and fighting negativity.
The Government Office on July 9 issued an official dispatch on Prime Minister Pham Minh Chinh’s directions requiring the acceleration of public investment disbursement for 2024.
Tuan expressed his confidence that LH, with its expertise and experience, would swiftly implement the urban area project, contributing to a modern urban landscape for the province.
With its strategic location, abundant workforce, and modern infrastructure, Vietnam holds significant potential to become a leading centre for power and electronics production in the region and the world.
The renewable energy workforce training and development centre, invested by Germany's GEO Group, is expected to be a cornerstone in shaping Binh Dinh as a renewable energy and innovation hub in central Vietnam, meeting the growing demand for skilled technical personnel in offshore wind, solar farms, and green hydrogen projects.
A notable trend is the shift toward satellite regions. With land scarcity and soaring prices in Ho Chi Minh City and Hanoi, investors are eyeing provinces like Hung Yen, Bac Ninh, and Hai Phong, which are benefiting from improved technical infrastructure and transport connectivity.
To further strengthen private-sector innovation, Bac Ninh plans to accelerate administrative reforms, build a digital, service-oriented government, and develop an integrated innovation ecosystem that connects businesses with domestic and international institutions, universities, and experts.
The participation of H&M, one of the world's largest fashion corporations, in Vietnam International Sourcing 2025 in Ho Chi Minh City in early September is considered a special highlight, opening up many cooperation opportunities for Vietnamese businesses in the fashion, textiles and sustainable supply chains.
This latest order builds on a previous agreement signed at the Singapore Airshow last year for 40 engines, bringing the total number of Trent 7000 engines ordered by the airline to 80.
Minister of Industry and Trade Nguyen Hong Dien acknowledged that despite concerted efforts by ministries and local authorities in combating fake and substandard goods, the situation remains highly complicated, attributing the persistent challenges to high profits luring numerous participants, increasingly sophisticated violations, limited resources within enforcement agencies.
The group also placed among the Top 5 energy companies in Southeast Asia and secured the top spot among the largest Vietnamese enterprises featured on the list.
The zone will cover 1,881 ha, comprising functional areas for production, logistics, trade and services, digital technology industry, information technology, and innovation.
Dung underlined several key objectives, including a comprehensive review of the legal framework governing SOEs, and called for updates that reflect international standards and support modern, transparent governance.
While the US market has become more difficult to access due to new tax policies, Australia could play the role of a trade cushion, helping to reduce shocks and maintain export momentum for Vietnam's shrimp industry.
Vietnam Cycle Expo 2025 will coincide with the Vietnam Sport Show 2025, an international exhibition on sports and outdoor entertainment, expected to attract more than 20,000 visitors in the three-day event.
Despite global economic uncertainties, Binh Duong has maintained strong momentum in both exports and industrial production during the first half of 2025.