Repairs to undersea cable scheduled to complete on July 7

Repairs to the Asia Africa Europe 1 (AAE-1) undersea fiber optic cable will be delayed to July 1 and expected to complete six days later, according to the managing board of the cable.
Hanoi (VNA) –Repairs to the Asia Africa Europe 1 (AAE-1) undersea fiber optic cable will bedelayed to July 1 and expected to complete six days later, according to themanaging board of the cable.

The undersea cable hada problem on its S1H.1 section on May 25, which caused disruptions to a part ofservices of domestic telecom providers.

Repairing work wasinitially scheduled to start on June 22 and finish on July 13. Although thestart date is postponed for eight days, repair time will be shortened.                                                                                                                                                                                       
As a result, Vietnam’sinternet connection with the world is projected to fully recover on July 7.

The AAE-1 is amongimportant submarine cable systems of Vietnam alongside four others of the Asia-AmericaGateway (AAG), the Asia-Pacific Gateway (APG), the TGN-Intra Asia Cable System(TGN-IA), and the South-East Asia - Middle East - Western Europe 3 (SMW-3)./.
VNA

See more

Cybersecurity incident response: Concrete actions needed

🌌 Cybersecurity incident response: Concrete actions needed

As Vietnam’s digital transformation accelerates, both the frequency and severity of cyberattacks are growing. The National Cybersecurity Association (NCA) reported that in 2024 alone, there were some 659,000 separate cybersecurity incidents, impacting around 46.15% of government agencies and businesses.
The ceremony to announce new NIC - Google initiatives (Photo: VNA)

💖 NIC – Google partnership powers Vietnam’s innovation: Deputy PM

Since 2022, more than 500 Vietnamese startups have engaged in Google’s Startup Academy, Google for Startups Accelerator, and Google Startup Masterclass. Nearly 100 of these firms received support to develop and improve their products, benefiting more than 300,000 customers and creating over 300 new jobs through successful fundraising and team expansion amidst Vietnam’s competitive economy.
Leaders of the Binh Duong Provincial People's Committee meet with a delegation from Taiwan (China)'s MiTAC Group. (Photo: VNA)

🧸 Tech giants eye Binh Duong as Vietnam's emerging high-tech hub

Over the past three decades, Binh Duong has cemented its status as one of Vietnam’s most dynamic industrial hubs, building a robust foundation in manufacturing, exports, and investment. The province now has 30 operational industrial parks spanning over 13,000 hectares, with an occupancy rate exceeding 90%.
Prime Minister Pham Minh Chinh (second, right) visits the division of nuclear science and engineering (NSE) in the Physics Department at the Royal Institute of Technology (KTH) of Sweden on June 13, 2025. (Photo: VNA)

🐬 PM calls for cooperation with Sweden in nuclear energy technology

The PM revealed Vietnam’s plan to develop nuclear power in the near future, and called on the Swedish side to assist Vietnam in developing and refining legal and policy frameworks for the use of nuclear energy for peaceful purposes; training and developing human resources; ensuring nuclear safety; and conducting training and drills to improve incident management capabilities.
{tk88 bet}|{tk88 bet}|{tk88 bet}|{tk88 bet}|{tk88 bet}|{tk88 bet}|{tk88 bet}|{tk88 bet}|{tk88 bet}|{tk88 bet}|